Location
Battery Park City

Completion
2011

Client
Goldman Sachs

Square Footage
30,000 SF

Design Architect
Remedios Studio and Office dA, Inc.

Executive Architect
Kohn Pederson Fox Associates (KPF)

LEED
Gold

Site #25 Facade & Atrium Upgrade

Sciame was responsible for the removal and replacement of approx. 30,000 SF of existing building envelope area while a 400+ key hotel, the Regal Theater Cinemas, and a food service tenant remain in operation. Facade removals also included large pre-cast concrete brick and granite faced panels, as well as an existing Marquee and canopy removal.

The new scope included re-fitting the newly exposed building areas with a high end curtain wall, storefronts, entrances and canopies. In order to best isolate the interior, Sciame planned and constructed weather walls prior to the existing facade removals which allowed tenant spaces to remain in operation.

In addition to the logistics associated with the 200 West Glass Canopy, significant steps were taken for overhead protection and sequencing the work. Sciame implemented creative solutions to create these work zones which satisfied the required overhead protection while simultaneously reducing the footprint of the actual construction work area.

We’re turning 50! As we count down to Sciame’s 50th anniversary on June 13th, we’re celebrating the moments that shaped us. For the next 50 days, we’ll be sharing one standout project a day in our “Countdown to 50”.

Thank you to our amazing clients, team, and friends! We wouldn’t be here without you.
...

177 9

Honoring 50 years of Sciame Construction and Frank’s recognition in City & State’s 50 Over 50 List. Thank you for your leadership and lasting impact on the city and the built environment! ...

134 8